Enforcement Notice

Date of notice:
18/04/2023
Required compliance:
03/10/2023
Remedial works completed:
11/04/2024
Notice served to:
HML PM Ltd
Property type:
Purpose Built Flats>=4 floors
Applies to:
Flats 35-41, MARINA PLACE, HAMPTON WICK, KT1 4BH
Served to:
, 9-11 The Quadrant, Richmond, Surrey TW9 1BP, TW9 1BP

Additional Information

Borough premises situated in: Richmond upon Thames

Responsibility of person on whom notice served: Owner

Applicable legislation: Article 30: Regulatory Reform (Fire Safety) Order 2005

Comments

  • The time allowed for completion of remedial works has been extended to 3 January 2024.

    17/10/2023

Articles

  • Article 8

    Failure to take general fire precautions to ensure the safety of persons on the premises.

    Implement the general fire precautions as identified by the fire risk assessment.

  • Article 9

    Failure to review the fire risk assessment.

    Implement regular program to review fire risk assessment.

  • Article 11

    Failure in the effective management of the preventive and protective measures.

    Implement arrangement for the effective planning, organisation, control, monitoring and review of the preventive and protective measures.

  • Article 14

    Failure to provide and/or maintain adequate and clearly indicated emergency routes and exits that lead to a place of safety.

    Ensure that adequate escape routes and exits leading to a place of safety are provided and that these are maintained clear and available for use at all times that the premises is occupied.

  • Article 15

    Failure to establish an appropriate emergency plan.

    Prepare/update emergency plan.